Significant Development at Blockade in Tail Race Tunnel of Neelum Jhelum Project

coal-tunnl
Significant Development at Blockade in Tail Race Tunnel of Neelum Jhelum Project Tunnel Collapse of 150 ft Length Restored on Eid Day Chairman WAPDA Asks For Resuming Power Generation From Project by End July

A significant development at the blockade in tail race tunnel of 969MW-Neelum Jhelum Hydropower Project has been achieved on Eid day. Tunnel collapse of 150 ft length has been restored. Restoration works are continuing during Eid Holidays.

Chairman WAPDA Engr Lt Gen Sajjad Ghani (Retd) visited Neelum Jhelum Hydropower Project today and witnessed construction activities on the remedial works. He appreciated the efforts of Project Team WAPDA, China Gezhouba Group Company (CGGC) and Consultants of the Project.

The Chairman was briefed that the remedial works for restoration of Neelum Jhelum Hydropower Project are under way in light of the report furnished by the International Panel of Experts. Hydraulic lining shutter is being installed inside the tail race tunnel for concrete lining, while the allied works are also continuing side by side. Risk analysis report by the Consultants is expected to be finalized during the next month. Chairman WAPDA directed Project Authorities to resume electricity generation from the Project by end July.

Related posts